Project Description

Equipment – 17 MMSCFD Process Plant needed 52 PSV’s replaced with pilot operated or larger orifices valves due to safety requirements for discharge to an enclosed system with off-site vent/flare arrangement

Scope – Provided engineering review of replacement plan, isometric drawings for all PSV discharge line changes, and assisted with construction

Facility Capacity – flare system was designed to flare the first 4 MMSCFD of gas, and vent any gas above 4 MMSCFD during an emergency

Unusual note: This project was accelerated by 8 weeks due to California wildfires that shut the plant down for ten days, two months ahead of scheduled shutdown